Design, drawings & permit
Site walk, drawings and a written specification naming dimensions, equipment models, tile, coping, decking and finish. Our office files the standard permit.
Pool Building Process · Step by Step
The pool building process at New Creation runs in four stages, from drawings and permits to the day the water goes in. The standard build is 8 to 10 weeks of weekday working days from excavation to fill.
Inground Pool Construction Stages
Site walk, drawings and a written specification naming dimensions, equipment models, tile, coping, decking and finish. Our office files the standard permit.
Georgia 811 marks utilities, the pool is dug to the drawn depths, plumbing is run, the steel cage is tied and the concrete shell is sprayed in place.
Six-inch waterline tile, coping, the pool deck and its drains, masonry and water features, then the Stonescapes® Mini Pebbles interior you chose.
The pool is filled, the Jandy® Pro-Series equipment is started, and you are walked through running your pool.
On Site · New Creation Pools Under Construction
Six short clips filmed on New Creation job sites in Georgia. No stock footage and no sound: just the work, from the first cut in the clay to the pebble finish.
The pool is cut into Georgia red clay to the drawn depths, with form boards set along the edge.
A tied rebar cage lines the floor and walls, with plumbing stubbed in before any concrete.
Concrete is shot over the steel to form the beam, walls and floor as one shell.
A raised stacked-stone wall with a stone cap and planter trough goes up beside the shell.
The concrete deck is poured and jointed, and the waterline tile is set.
The pebble interior goes onto the steps and walls, then is rinsed to bring out the stone.
Pool Build Timeline
Eight to ten weeks of Monday–Friday working days is our standard timeframe for a custom pool. A pool house, detached garage or large hardscape built in the same project adds to that.
Before construction starts, permit review time depends on your city or county.
Build Questions, Answered
What homeowners ask most once the design is settled.
See pool types and finishesOur standard timeframe is 8 to 10 weeks of Monday–Friday working days, counted from the morning of excavation to the day the pool is filling. Weekends, holidays and rain days are not counted.
Rain is the usual cause: digging, concrete and decking all need dry ground. Permit review, changes to the plan after work has started, and adding a pool house or detached garage to the same project can also move the date.
Our office prepares and files the standard permit and calls in every inspection. Georgia 811 is called to mark underground utilities before excavation. The permit and fence guide lists the office for each town.
Yes. A start date is set once the agreement is signed, the deposit is received and a survey or plat of your property is in hand.
In four stages tied to construction progress: 25% at signing for planning, drawings and permitting, 35% before excavation, 35% for decking, masonry, coping and interior finish, and 5% at final completion, startup and walkthrough.
Yes. Place a full-size pool on your own lawn with the backyard pool visualizer, or shape it in the 3D pool studio.